15. Moving in, Composting Toilet, Pantry

2nd of July - Flue casing done, heater pumping, its time to move in!!!!! There is still a lot to do. But we've got a comfy bed and heat so we are in.
3rd July - Starting to get visitors already! Nobbie chillin with Em. Temporary kitchen bench tops. No drawer fronts but it will be functional soon!
More drawer fronts and stainless handles. Bench tops to come. This is sort of a hallway section but Hudsons room spills into this area with the curtain open. We didn't want to waste space having a separate hallway section walled off from the rooms.
Hudsons cosy little room.
7th July - Digging a line trench for the composting toilet. This leads to an absorption trench about 25m away from the bus and is a shallow grave sized trench with gravel, ag pipe and hessian cloth. The excess liquid from the toilet ends up here.